How to Make a Gantt Chart (Step by Step, With an Example)
Turn a project into a clear schedule. What belongs in a Gantt chart, how dependencies and milestones work, and the mistakes that make a plan useless after a week.
Updated · 5 min read
A to-do list says what needs doing, but it doesn't say whether it all fits. A Gantt chart adds the missing dimension. Each task becomes a bar on a calendar, so you can see what runs in parallel, what has to wait, and when the project will really end.
The format is named after Henry Gantt, who popularized it in the 1910s. It has lasted because it answers the question everyone in a project asks: are we on track?
What a Gantt chart shows
Every Gantt chart has the same few parts:
- Tasks, listed down the left side
- A time axis across the top, in days, weeks or months
- Bars, which show when each task starts and how long it runs
- Dependencies, shown as arrows or links between tasks
- Milestones, usually drawn as diamonds
- Progress, shown as a filled part of each bar
When a Gantt chart helps
It suits projects with a clear start and end, where tasks depend on each other: building a house, launching a website, organizing an event, moving an office or writing a thesis.
It suits ongoing work less. A support queue or a team working in short sprints will get more from a simple board. If your project has no real dependencies, a timeline showing the key dates may be all you need.
Step 1: List the tasks
Start with the finished result and work backwards. What has to be true for the project to be done? Break each big item down until a task is something one person or team can finish in a reasonable time.
A good rule of thumb is that a task should take between a day and two weeks. Anything longer hides uncertainty, and anything shorter makes the chart impossible to maintain.
Group tasks into phases. Phases make long lists readable, and they give you natural points to review progress.
Step 2: Estimate durations
Ask the person who will do the work, not the person who wants it done. Use working days, and allow for weekends, holidays and other commitments. If a task feels impossible to estimate, it's probably too big, so split it.
Step 3: Add the dependencies
This step turns a colorful calendar into a working plan. Most dependencies are "finish to start": task B can't begin until task A is done. You can't paint a wall before the plaster has dried, and you can't test a page that hasn't been built.
Only link tasks that truly depend on each other. If two tasks merely tend to happen in that order, leave them unlinked, as false dependencies make your schedule look longer than it is.
In the Gantt chart maker, you give a task its predecessors in the After column and leave the start date empty. It then starts as soon as they finish, and if an earlier task moves, everything behind it moves along.
Step 4: Add milestones
Milestones mark moments, not work. They have no duration: design approved, contract signed, site live. Use them for decisions and handovers, as these are the points where projects usually stall. They also make good reporting points, because "design approved on the 14th" says more than "design is 80% done."
Step 5: Check the critical path
The critical path is the longest chain of dependent tasks from start to finish. It sets the earliest possible end date. Any delay on that chain delays the whole project, while tasks off the chain have some slack.
This is why adding people to a side task doesn't help if the bottleneck sits elsewhere. When a deadline is tight, look at the critical path first.
A worked example
Here's a small website launch, planned in working days:
| Task | Duration | After |
|---|---|---|
| 1. Write brief | 3 days | |
| 2. Design pages | 10 days | 1 |
| 3. Write content | 8 days | 1 |
| 4. Milestone: design approved | 0 days | 2 |
| 5. Build site | 12 days | 4 |
| 6. Add content | 3 days | 3, 5 |
| 7. Test and fix | 5 days | 6 |
| 8. Milestone: launch | 0 days | 7 |
The critical path runs 1 → 2 → 4 → 5 → 6 → 7, which adds up to 33 working days, or just under seven weeks. Writing content takes 8 days and has plenty of slack, because the site won't be ready for it until day 25. A delay of a week there changes nothing, but a week lost on the design moves the launch by a week.
Without the chart, you might well have put your worry in the wrong place.
Common mistakes
Too much detail. A chart with 300 tasks is out of date by Wednesday, and nobody will update it. Keep the chart at the level you can maintain, and let teams track the detail themselves.
No buffer. A schedule in which everything goes perfectly is a wish. Add contingency before key milestones, and make it visible, so it isn't quietly used up.
Ignoring capacity. Two tasks can overlap on the chart yet need the same person. Check who's doing what, especially around holidays.
Drawing it once. A Gantt chart is only useful if it reflects reality. Update progress weekly and move the dates when things change.
Using it to hide bad news. If the end date moves, the chart has done its job. Better to know now than the day before launch.
Making one without project software
You don't need a project management system for a chart like this. You can build one in a spreadsheet with a stacked bar, but dependencies won't move for you. The Gantt chart maker takes a task list, including a CSV from a spreadsheet, and lets you choose days, weeks or months. You can download the result as PNG or SVG, or print it.
For a simple comparison of task lengths or budget by phase, a regular bar chart will often read better in a report.