Gantt Chart Maker
Plan tasks, phases, milestones and dependencies on a clear Gantt chart and export it.
How to use the Gantt Chart Maker
- 1Enter your tasks with a start date and an end date or a number of days, or import a CSV.
- 2Add phases, milestones, progress and the tasks each one waits for.
- 3Pick the time scale and style, then download PNG or SVG or print the chart.
About Gantt Chart Maker
The Gantt Chart Maker turns a list of tasks into a project schedule. Each task has a name, an optional phase, a start date and either an end date or a duration in days, plus how much of it is done. A task can wait for other tasks: name them, or give their row numbers, under After, leave the start date empty, and it begins as soon as they are finished. Milestones mark single dates such as a kickoff, a sign-off or a launch. Tasks can be imported from a CSV or spreadsheet export and downloaded again as CSV.
The chart shows days, weeks or months, with a two-row date header and an adjustable column width. Working days only skips Saturdays and Sundays when durations are counted, and weekends can be shaded. Tasks are grouped under their phase with a summary bar per phase, dependency arrows connect each task to the ones it follows, bars fill up with their progress, and a red line marks today. A task list on the left shows names, start and end dates and durations, or the names move next to their bars. Colors, font, text size and background are adjustable.
Project managers, teams, students and freelancers use a Gantt chart to plan a project, show who waits for what, report progress to a client or put a schedule into a slide or report. Download the chart as PNG or SVG, copy it to the clipboard or print it straight from the page. Everything runs in your browser; the tasks are never uploaded.
Frequently asked questions
What is a Gantt chart?
A Gantt chart is a bar chart of a project schedule. Each task is a horizontal bar from its start to its end date on a timeline, so you can see at a glance what happens when, what overlaps and how long the whole project takes.
How do task dependencies work?
Under After, list the tasks a task waits for, by name or row number, separated by commas. If the task has no start date of its own, it starts the day after the last of them finishes, and an arrow connects them in the chart. A dependency loop is reported as a warning.
How is the end date calculated from the duration?
The start day counts as the first day, so a 5-day task starting on Monday ends on Friday. With working days only, Saturdays and Sundays are skipped, so a 10-day task takes two calendar weeks. An end date you type always wins over the duration.
How do I add a milestone?
Set the type to Milestone and give it a date, or let it follow another task. It is drawn as a diamond on that day instead of a bar.
Can I import tasks from Excel?
Yes. Save the sheet as CSV or copy the rows, then use Import. Columns such as Task, Phase, Start, End, Duration, % Complete and Predecessors are matched by name, and dates like 2026-11-02, 02.11.2026 or 11/02/2026 are recognized.
Guides
More in Charts & Diagrams
Create bar, line, area, pie and scatter charts from your data.
Make grouped, stacked and horizontal bar graphs in seconds.
Plot trends over time as line or area graphs.